Baba Ahmad Earth Dam Construction


PROJECT

Baba Ahmad dam operation

CLIENT

West Azarbaijan  regional water company

YEAR 

2008

STATUS

Completed

Project Duration

24 Month


Project specification:

Storage net volume : 1000000 cubic meter

Height from sea level: 34 meter

Inlet water volume: 378 million cubic meter

Excavation volume:150000 cubic meter

Embankment volume: 450000

ØDiversion and basin systems : In order to ensure safety during the construction of dams , water diversion pipe is predicted  by using the two rows of steel tubes with a diameter of 1200 mm.
ØWeir : this weir is  Ogee weir with a width of 5 m.
.